Knostrop Waste Treatment Plant

Client | Yorkshire Water

Main Contractor | Earth Tech Morrisons

Timeline | 18 Months

The Project

This project involved constructing an area designated for the set-down of cabins, power generation, and welfare facilities. The complete treatment plant was decommissioned, and all redundant metal waste apparatus and concrete structures were removed, with the area compacted afterward. Drilling and pressure grouting were supervised to neutralise volatile gases, fill voids, and stabilise the sub-structure. Large and small diameter surface water and sewer systems, as well as MDPE plumbing mains, were installed site-wide. Finally, the entire area was landscaped, including the removal of welfare facilities and the landscaping of the laydown areas.